Project length - 3 weeks
Main contractor - TMP Electrical Ltd (part of the Morhen group)
Project Includes:
- Installation of a Distribution Board and Feed to Depot
- Installing Sixteen 110v Power Reels from Inline Transformers
- Installation of Twenty Double 13A Sockets
- Building and Installation of a Framework and Four More External 110v Charging Reels
- Design and Installation of a WIFI and CCTV and Alarm System
- Design and Installation of External Flood Lighting
- Instillation of Two Roller Shutter Door Supplies
This job was for the largest platform access company in the UK, allowing them to drop units off at a storage location and charge all means of equipment, ready for their next hire.
Project length - 10 Weeks
Main contractor - Total Facility's Management LTD
Project Includes:
- Installation of New Warehouse Lighting Distribution Board and Containment
- Warehouse Lighting Design and Installation Working Alongside Dextra lighting
- Design and Installation of Forklift MHE charging area
- Accompanying the DB Install With an Inline Generator Change Over Switch
This job was for our first large client back in 2020. A crips warehouse in the midlands, the quality of our service and work, has led us on to 4 years of working with them now on bigger and more complex projects.
Project length - 9 Weeks
Main contractor - TMP Electrical LTD (part of the Morhen group)
Project Includes:
- Design and Installation of the Buildings Incoming Feed and Panel
- Installation of mains and contaminant
- Door Access Controls (Paxton system)
- CCTV and Alarm
- Fire Alarm Install, Design and Commission
- Data cabling, HDMI and Connections of Cab & Field Ends
- Fibre Into the Building and Connections
- Wi-Fi Design and Installation
- General and Emergency Lighting, Design and Install
- General Power Install Along with Desk Towers
This job was for the largest Logistics company in the UK. We have done approximately 20 large scale projects with them over the past 3 years and have built a great relationship, delivering on time and in budget every time.
This is a 2-storey office build out of open plan cabins and cladded around the outside, this building therefore falls under the temporary building regs and guidelines, helping the client on building regs and permissions.
Project length - 10 Days
Main contractor - TMP Electrical LTD (part of the Morhen group)
Project Includes:
- Installation of Framework, Housing Sockets, Commando Sockets, Lighting, Data Points and Air Lines
- Tray Work on the Fence Line Incorporating Lights and Sockets
- Pit Lighting
- Heating Supplies for Overhead Blow Heaters.
This project was for Scania Warrington, a large logistics company was wanting an onsite workshop for Scania employees to reduce the travel of 100's of tractor units across Warrington, Saving the client thousands on fuel and driver wages.
Project length - 3 Months
Main contractor - TMP Electrical LTD (part of the Morhen group)
Project Includes:
- Design and Installation of Warehouse Lighting
- Design and Installation of Office Lighting
- General Power and Computer Floor Buss Bar Install
- Wi-Fi System
- General Data Cabling, Fibre and Door Access System
- Turnstile Access
- MHE Forklift Charging Area
- Lighting Distribution Boards and Buss Bar along with 2 Generator Change Over Switches
- Chiller Units for Warehouse Temperature Control
- Pump House Feed for Sprinkler System
- CCTV Install